Review the Control Account information
Due Date: Sunday by 11:59pm Total Points: 100 Instructions: Review the Control Account information, and determine the current status for each of the work packages listed. Calculate the SV, CV, SPI, CPI, EAC, VAC, and TCPI for each of the following work packages:
Work Package EV Techniq
ue
PV or BCWS
EV or BCWP
AC or ACWP
CV SV SPI EAC VAC TCPI
1.1.1.1.1. Hull – Order Raw Steel
50/50 $310 m $155 m $155 m
1.1.1.1.2. Hull – Order Polymer Material
50/50 $9 m $4.5 m $1m
1.2.1. Final Certified Bow Redesign
% complet
e
$4 m $3.7 m $4.1 m
1.2.2.1 Systems Engineering Planning– PMB Development
0/100 $ 1.2 m $1.2 m $1 mil
1.3.2. Project Management Planning – PMB development
0/100 $.5 m $.5 m $.3 m
PMG640 – Project Scheduling and Cost Planning
Unit 7 Assignment: PMB
Requirements:
Use this MS Word file to complete your assignment and submit via Blackboard.
Save your files using the following filename convention:
o PMB – FirstName_LastName
Be sure to read the criteria, by which your paper/project will be evaluated, before you write, and again after you write.
Evaluation Rubric for Unit 7: PMB Assignment
CRITERIA Deficient
Needs
Improvement Proficient
Exemplary
0 – 59 Points 60 – 79 Points 80 – 99 Points 100 Points
Number of Correct Values Calculated
Less than 17
correct values
calculated.
18 to 23 correct
values calculated.
24 to 29 correct
values
calculated.
30 correct values calculated.