Work Breakdown Structure and Activities for the Cell Phone Design Project

Work Breakdown Structure and Activities for the Cell Phone Design Project

 Work Breakdown Structure and Activities for the Cell Phone Design Project

You work for a company that makes cell phones and have been made project manager for the design of a new cell phone. Your supervisors have already scoped the project, so you have a list showing the work breakdown structure, and this includes major project activities. You must plan the project schedule and calculate project duration. Your boss wants the schedule on his desk tomorrow morning!     You have been given the information in Exhibit 4.13. It includes all the activities required in the project and the duration of each activity. Also, dependencies between the activities have been identified. Remember that the preceding activity must be fully completed before work on the following activity can be started.    Your project is divided into five major subprojects. Subproject “P” involves developing specifications for the new cell phone. Here, decisions related to such things as battery life, size of the phone, and features need to be made. These details are based on how a customer uses the cell phone. These user specifications are redefined in terms that have meaning to the subcontractors that will actually make the new cell phone in subproject “S” supplier specifications. These involve engineering details for how the product will perform.     The individual components that make up the product are the focus of subproject “D.” Subproject “I” brings all the components together, and a working prototype is built and tested.     Finally, in subproject “V,” suppliers are selected and contracts are negotiated.

Exhibit 4.13: Work Breakdown Structure and Activities for the Cell Phone Design Project

MAJOR SUBPROJECTS/ACTIVITIES    ACTIVITYIDENTIFICATION   DEPENDENCY    DURATION (WEEKS) Product Specifications (P)

Market research                                                 P1                                       —                        6

Overall product specifications                      P2                                         P1                         4

Hardware                                                 P3                                      P2                            4

Software                                                P4                                        P3                            6

Supplier specifications (S)

Hardware                                                    S1                                    P4                           5                                                Software                                              S2                                     P4                           6

Product design (D)

Battery                                                               D1                                   S1                              1                                  Display                                                            D2                                  S1                                6

Camera                                                             D3                                    S1                             1

Outer cover                                                 D4                                D1,D2, D34                    4

Product integration (I)

Hardware                                                            I1                                     D4                         3

User interface                                                     I2                                     D2                        4

Software coding                                                I3                                      I2                         4

Prototype testing                                            I4                                       I1, I3                        5

Subcontracting (V)

Suppliers selection                                                        V1                                  S1 ,S2                     10

Contract negotiation                                                    V2                                   I4, V1                         6

a. Calculate the start and finish times for each activity. (Leave no cells blank – be certain to enter “0” wherever required.)

Activity      EST     EFT     LST     LFTP1

P2

P3

P4

S1

S2

D1

D2

D3

D4

I1

I2

I3

I4

V1

V2

b. Determine the minimum number of weeks for completing the project.

c. Find the activities that are on the critical path for completing the project in the shortest time.

multiple choice

  • P1-P2-P3-P4-S1-D2-D4-I1-I4-V2
  • P1-P2-P3-P4-S1-D2-I2-I3-I4-V2
  • P1-P2-P3-P4-S1-D3-D4-I1-I4-V2
  • P1-P2-P3-P4-S1-D1-D4-I1-I4-V2

Order Solution Now

Our Service Charter

1. Professional & Expert Writers: Homework Place only hires the best. Our writers are specially selected and recruited, after which they undergo further training to perfect their skills for specialization purposes. Moreover, our writers are holders of masters and Ph.D. degrees. They have impressive academic records, besides being native English speakers.

2. Top Quality Papers: Our customers are always guaranteed papers that exceed their expectations. All our writers have +5 years of experience. This implies that all papers are written by individuals who are experts in their fields. In addition, the quality team reviews all the papers before sending them to the customers.

3. Plagiarism-Free Papers: All papers provided by Homework Place are written from scratch. Appropriate referencing and citation of key information are followed. Plagiarism checkers are used by the Quality assurance team and our editors just to double-check that there are no instances of plagiarism.

4. Timely Delivery: Time wasted is equivalent to a failed dedication and commitment. Homework Places is known for timely delivery of any pending customer orders. Customers are well informed of the progress of their papers to ensure they keep track of what the writer is providing before the final draft is sent for grading.

5. Affordable Prices: Our prices are fairly structured to fit all groups. Any customer willing to place their assignments with us can do so at very affordable prices. In addition, our customers enjoy regular discounts and bonuses.

6. 24/7 Customer Support: At Homework Place, we have put in place a team of experts who answer all customer inquiries promptly. The best part is the ever-availability of the team. Customers can make inquiries anytime.